The ENI Livorno Affair: Biofuels, Bioplastics and the €500 Million Question

Written by

·

ENI Livorno refinery with Italian, European Union and ENI flags

The ENI Livorno Affair: Biofuels, Bioplastics and the €500 Million Question

An investigation into the industrial, environmental and financial foundations of ENI’s Livorno transformation, the economics of the circular economy and the European Investment Bank’s decision to finance the project.

By Axel Barrett — Bioplastics News — 29 November 2026


Executive summary

On 24 July 2025, the European Investment Bank (EIB) and Italian energy multinational ENI announced a €500 million, 15-year financing agreement to support the conversion of ENI’s conventional petroleum refinery in Livorno, Tuscany, into a biorefinery.

Presented as an investment in Europe’s energy transition, the project is intended to increase the production of renewable fuels, reduce greenhouse gas emissions, strengthen European energy security and provide an industrial future for an existing refinery.

At first sight, the proposition appears straightforward: replace fossil raw materials with biological feedstock and transform an ageing industrial facility into an asset compatible with Europe’s decarbonisation objectives.

However, a closer examination of official documents, corporate disclosures, financial statements, environmental assessments, parliamentary records and the wider ENI industrial ecosystem reveals a considerably more complex picture.

Among the findings of this investigation:

  • An official regional document estimated the investment at €420 million in May 2024. The EIB subsequently estimated the project cost at €741 million.
  • ENI awarded an approximately €300 million construction contract to Saipem, a company jointly controlled by ENI and CDP Equity. Saipem classified the contract as a related-party transaction of major significance.
  • The publicly available documentation examined for this investigation does not identify competing bidders or disclose an independent price benchmark for that contract.
  • Shortly before the EIB approved its financing, private equity firm KKR completed transactions involving approximately €3.6 billion in proceeds for the ENI group, including a €500 million capital increase in Enilive.
  • ENI has subsequently confirmed that its preference for EIB financing did not result from difficulties obtaining private financing.
  • The Livorno refinery occupies land included in an Italian national environmental remediation site.
  • ENI has confirmed that groundwater containment and treatment remain necessary at the site.
  • Approximately 180,000 tonnes of material, predominantly excavated soil and rocks, were managed during the conversion at a cost of approximately €40 million.
  • The EIB’s public environmental assessment does not explicitly address the refinery’s historical contamination or its outstanding remediation liabilities.
  • The EIB’s environmental assessment lists no specific environmental condition precedent to disbursement, although other environmental undertakings and contractual obligations apply.
  • The hydrogen production plant uses methane-based technology, raising questions about continued dependence on fossil resources.
  • The value of the hydrogen plant construction contract increased from €123.8 million to €136.2 million, while its commissioning-related milestones moved into 2027.
  • ENI’s agricultural supply chain extends across continents and benefits from substantial international development financing.
  • ENI has confirmed that rapeseed imported into Kenya from South Africa accounted for a substantial portion of its Kenyan oilseed feedstock exports to Italy in 2025.
  • Official Tuscan documents identify separate proposals for gasification and biomethanization facilities associated with the Livorno refinery site.
  • One of these proposals explicitly envisaged processing rejects from organic waste composting facilities.
  • ENI, through Versalis, owns Novamont, one of Europe’s principal producers of compostable plastics.
  • The EIB has calculated annual greenhouse gas savings of 660,500 tonnes of CO₂ equivalent, but the detailed assumptions necessary to reproduce that calculation have not been publicly disclosed in its environmental summary.
  • The recorded publication date of the EIB project summary falls after both financing approval and signature, despite the bank’s general policy of publishing project summaries before approval.
  • An institutional relationship exists between an EIB vice-president who signed the financing agreement and an Italian think tank maintaining a strategic partnership with ENI. The position was publicly disclosed and unpaid.

These findings do not individually or collectively establish corruption.

They do, however, raise substantial questions concerning financial additionality, procurement, environmental due diligence, institutional transparency, industrial viability and the accounting of Europe’s circular economy.

The purpose of this investigation is to examine those questions together rather than treating each component of the project in isolation.


1. Livorno: the transformation of a petroleum refinery

The Livorno refinery is located in the industrial area of Stagno, between Livorno and Collesalvetti, on the Tuscan coast.

For decades, the site has been part of Italy’s petroleum refining infrastructure, benefiting from maritime access, storage facilities, established industrial utilities and connections to domestic fuel distribution networks.

In October 2022, ENI announced its intention to examine the conversion of the refinery into a biorefinery.

In January 2024, the company confirmed that it would proceed with the transformation.

The conversion involved progressively discontinuing conventional crude oil processing and replacing existing fossil fuel production activities with facilities producing hydrogenated biofuels.

ENI describes the project as following the industrial model previously implemented at its Venice and Gela biorefineries.

The strategic advantages of converting existing industrial facilities are evident. Such sites already possess infrastructure that would otherwise have to be constructed from scratch. They also have experienced workers, logistical connections and existing relationships with industrial suppliers.

However, converting a refinery also raises a fundamental financial question.

What was the economic condition of the original industrial asset?

The publicly available project documentation provides considerable information about the planned investment. It provides much less information about the historical financial performance of the refinery being converted.

Bioplastics News has not identified a continuous series of independently verifiable, site-specific financial statements establishing Livorno’s historical profitability, operating losses, maintenance expenditure, asset impairments and capital requirements.

Without those figures, it is difficult to compare the economics of three possible alternatives:

  1. Maintaining conventional refinery operations.
  2. Closing the refinery, dismantling the installations and addressing outstanding environmental liabilities.
  3. Converting the existing site into a publicly financed biorefinery.

Interestingly, the possibility of ENI withdrawing from Livorno was already discussed in the Italian Parliament in 2008 and 2009. Parliamentary records refer to the possible sale of the refinery and the difficulties surrounding industrial development in an environmentally compromised area.

The industrial future of Livorno was therefore a subject of concern long before the contemporary biofuel strategy.

Was the conversion primarily motivated by the prospect of a commercially attractive new business, by the need to preserve an existing industrial asset, or by a combination of both?

The distinction matters because the economic and environmental costs associated with the original refinery may influence the financial rationale of the conversion.

What would permanent closure have cost ENI? What alternative industrial investments were considered? What was the residual accounting value of the refinery before its transformation?

And, most importantly, did the European Investment Bank examine these alternatives before approving its financing?


2. What exactly is being built?

The Livorno biorefinery project comprises three principal new industrial installations.

InstallationFunction
Feedstock pre-treatment unitRemoves impurities and prepares biological oils and fats for industrial processing.
Ecofining unitConverts prepared oils and fats into hydrogenated biofuels.
Hydrogen production unitProduces the hydrogen required for the conversion process using methane-based technology.

The Ecofining technology was developed by ENI and Honeywell UOP.

Unlike conventional biodiesel production, hydrogenated vegetable oil production requires substantial hydrogen input to transform oils and fats into hydrocarbons compatible with existing fuel infrastructure.

The EIB identifies a planned annual processing capacity of approximately 530,000 tonnes of biomass feedstock and a production facility with a capacity of approximately 500,000 tonnes per year.

Potential products include HVO diesel, renewable naphtha and bio-LPG. The wider ENI strategy also envisages sustainable aviation fuel production.

These figures describe planned industrial capacity, not demonstrated commercial production.

The distinction between feedstock input capacity, final product capacity and the capacity of the wider refinery complex is important. Different environmental and corporate documents use different project boundaries when presenting industrial figures.

A complete reconciliation of those boundaries would help establish precisely what infrastructure the EIB has agreed to finance.

The existence of a dedicated methane-based hydrogen production plant is particularly important.

The project is presented as replacing fossil resources with renewable raw materials, yet its industrial process continues to require hydrogen that can be manufactured from fossil natural gas.

This does not automatically invalidate the project’s environmental benefits. It does mean that the environmental performance of Livorno cannot be assessed simply by examining the biological origin of its oils and fats.

The entire industrial process must be considered.

The Tuscany Region’s official bulletin of 15 May 2024 (source 29) also identifies the new hydrogen installation as intended to supply existing lubricant and solvent production facilities, as well as the new biorefining section. If the hydrogen installation is eligible for EIB financing, how are its investment costs allocated between renewable fuel production and existing industrial operations? The public documentation does not establish that the EIB loan finances those conventional activities.


3. From €420 million to €741 million

On 15 May 2024, the Official Bulletin of the Tuscany Region published an estimated investment value for the Livorno biorefinery of approximately €420 million, including VAT and excluding contingencies.

The European Investment Bank subsequently estimated the total project cost at €741 million.

Investment estimateAmount
Tuscany Region, May 2024€420 million
European Investment Bank, 2025€741 million
Difference€321 million
Indicative difference in percentage terms76.4%

A €321 million difference between two published investment estimates is material.

It would nevertheless be premature to describe the entire difference as a cost overrun.

The original regional estimate and the later EIB estimate may incorporate different project boundaries, accounting treatments, contingencies, infrastructure requirements or construction costs.

The earlier figure expressly excluded contingencies. That qualification must be taken into account.

However, the existence of potentially legitimate explanations does not remove the need for an explanation.

What changed between May 2024 and June 2025?

Did ENI underestimate the original construction cost? Were additional installations incorporated? Were significant environmental liabilities discovered? Did the scope of the hydrogen plant change? Were related-party engineering, project management or waste treatment costs added?

The original estimate also predates the formal signature of the €300 million Saipem construction contract in November 2024.

The relationship between these developments deserves examination.

The EIB should be able to reconcile its €741 million estimate with earlier project budgets and explain which expenditure is eligible for financing.

That reconciliation would provide a considerably clearer picture of the economic evolution of the project.


4. The European Investment Bank: €500 million in financing

The EIB’s public project register identifies the operation as project 2024-0694 — ENI BIOREFINERY.

Its principal figures are:

ItemAmount
Estimated project cost€741 million
EIB financing€500 million
Remaining estimated financing requirement€241 million
EIB financing as a proportion of project cost67.5%
Loan duration15 years

The €500 million represents a loan, not a grant.

This distinction is essential. ENI has repayment obligations, and the financing cannot accurately be described as an outright transfer of €500 million in subsidies.

Nevertheless, the economic benefits of public-bank financing can be considerable.

The EIB itself identifies financing advantages for ENI, including improved financing conditions and diversification of capital sources.

The bank has also introduced enhanced financing support for qualifying projects under REPowerEU. The proportion of project costs financed at Livorno is therefore not, in itself, evidence of an irregularity.

The central question is whether the public-policy contribution delivered by this particular investment justifies the financing advantages granted to ENI.

An unusually revealing explanation can be found in ENI’s answers to shareholders ahead of its 2026 general meeting.

Asked about the EIB loans for Livorno and Sannazzaro, ENI explained that the loans have 15-year maturities and variable interest rates indexed to Euribor, with spreads slightly more favourable than alternative financing sources.

ENI also stated that its preference for EIB financing did not arise from difficulties accessing private capital.

The company described the financing as a strategic and economic decision.

This is a particularly important admission.

ENI is not a small industrial company unable to obtain financing from conventional commercial banks. It is a multinational energy group with extensive access to capital markets.

The relevant issue is therefore financial additionality.

What does the European Investment Bank contribute that the private financial markets could not deliver on comparable terms?

Could the Livorno project have proceeded without the EIB?

Would ENI have invested the same amount using its own resources or commercial financing?

What measurable environmental, industrial or social benefits depend specifically on the EIB’s involvement?

It is entirely possible for a public development bank to finance a commercially viable multinational project for policy reasons. Financial distress is not a prerequisite for EIB financing.

But the more financially capable the borrower, the more important it becomes to demonstrate the additional public value of the financing.


5. KKR, Enilive and the financial beneficiaries

The chronology of ENI’s relationship with American investment firm KKR adds another dimension to the financing question.

On 6 March 2025, ENI announced completion of KKR’s acquisition of an initial 25% stake in Enilive.

On 11 April 2025, ENI announced completion of an additional transaction increasing KKR’s ownership to 30%.

According to ENI, the combined transactions generated approximately €3.6 billion for the ENI group, including a €500 million capital increase in Enilive to support its growth programme.

The transactions were based on a valuation of €11.75 billion for Enilive’s entire equity.

Less than three months later, the EIB approved its €500 million financing for the Livorno conversion.

DateFinancial development
6 March 2025KKR completes initial 25% investment in Enilive.
11 April 2025KKR increases its stake to 30%.
24 June 2025EIB approves €500 million Livorno financing.
23 July 2025Financing signature recorded in the EIB register.
24 July 2025Financing agreement publicly announced.

There is nothing inherently improper about combining private equity investment, corporate financing and public-bank lending.

Nevertheless, the sequencing raises questions about capital allocation and the ultimate distribution of economic benefits.

Was the anticipated EIB financing incorporated into Enilive’s valuation?

Was Livorno included in KKR’s investment assumptions?

Was KKR informed of the EIB negotiations before completing its investment?

What proportion of the €500 million Enilive capital increase was allocated to Livorno?

Which ENI group entity will ultimately own the completed biorefinery assets? Which entity will record the associated earnings, operating expenses, depreciation and financial costs?

The EIB identifies ENI S.p.A. as the project promoter. ENI presents Livorno within Enilive’s broader industrial strategy. In addition, the Italian environmental authorities identify ENI Industrial Evolution as the promoter of updated environmental procedures.

These distinctions are commercially and legally relevant.

If ENI borrows money on favourable terms to construct infrastructure that ultimately generates returns for a subsidiary in which a private equity investor holds 30%, the allocation of financing costs, liabilities and economic benefits deserves transparency.

The question is not whether KKR is entitled to benefit from its investment.

The question is whether the EIB assessed the extent to which its financing advantages would accrue to private shareholders, and how those advantages were justified in relation to European public-policy objectives.


6. Who received the construction contracts?

On 15 July 2024, Confindustria Livorno Massa Carrara published the names of the principal contractors associated with the three new installations.

The companies were identified following an ENI procurement roadshow intended to present contracting opportunities to local industrial businesses.

Production unitPrincipal contractorsDisclosed contract value
Feedstock pre-treatmentPower Project Consulting, Cestaro Rossi and Maiorana Costruzioni€125 million
Ecofining and interconnecting infrastructureSaipemApproximately €300 million
Hydrogen productionKT – Kinetics Technology, part of MAIRE GroupInitially €123.8 million
Combined indicative original value€548.8 million

The €125 million figure appears in Cestaro Rossi’s corporate project documentation. Confindustria identifies Maiorana Costruzioni as an additional participant in the temporary consortium.

The precise allocation of revenue and responsibilities among the consortium members has not been established.

The three principal contract values represent a substantial proportion of the EIB’s estimated €741 million project budget.

The combined original disclosed value is approximately €192.2 million below the overall estimate.

This difference cannot automatically be attributed to unexplained expenditure. It could include land preparation, owner-supplied equipment, utilities, engineering, financing costs, contingencies and other work outside the principal construction contracts.

Nevertheless, a detailed capital expenditure breakdown is needed.

It would also be useful to establish whether changes to the original contracts have been incorporated into the EIB’s estimate and whether further increases are expected.

The identities of the smaller subcontractors, their beneficial owners and the mechanisms through which their contracts were awarded remain relevant areas for further examination.

No evidence has been identified establishing that the three smaller pre-treatment contractors are secretly controlled by ENI or that their participation in the project is improper.


7. Saipem: the €300 million related-party transaction

Of the principal construction contracts, Saipem’s deserves particular attention.

Saipem is a major international engineering and construction company with extensive experience in energy infrastructure.

It is also jointly controlled by ENI and CDP Equity.

Corporate disclosures identify their respective shareholdings as:

ShareholderOwnership of Saipem
ENI S.p.A.21.19%
CDP Equity S.p.A.12.82%

Their joint control is exercised through a shareholder agreement.

The relationship between ENI and Saipem predates the Livorno construction contract.

On 6 November 2023, ENI and Saipem announced a strategic cooperation agreement concerning biorefining.

The agreement covered engineering studies and the potential construction of facilities using ENI’s biofuel technologies.

Saipem subsequently undertook feasibility studies and front-end engineering design for Livorno.

On 22 November 2024, ENI and Saipem formally signed an engineering, procurement and construction contract worth approximately €300 million.

In its 2024 annual report, Saipem disclosed the Livorno contract as a related-party transaction exceeding its major-significance threshold.

The company nevertheless classified the contract as an ordinary transaction conducted under conditions equivalent to market or standard conditions.

The transaction was reported to CONSOB, Italy’s financial markets regulator.

This distinction is fundamental.

A related-party transaction is not necessarily an improper transaction. Companies routinely conduct legitimate business with subsidiaries, shareholders and affiliated entities.

However, the existence of a corporate relationship between the purchaser and the contractor makes the verification of pricing and contractual conditions particularly important.

How was the approximately €300 million price established?

Was a competitive tender organised?

Did ENI receive competing offers from independent engineering companies?

Which companies were invited to submit bids?

Did Saipem’s involvement in preliminary engineering and feasibility studies provide it with a commercial advantage in the subsequent construction procurement?

Was the transaction independently benchmarked?

Were alternative engineering or construction arrangements evaluated?

Bioplastics News has not identified a publicly available competitive tender notice or a list of competing bidders for the €300 million contract.

This does not establish that no competitive process occurred.

Nor does it establish that Saipem’s price was inflated.

It means that the evidence necessary to independently verify the pricing has not been identified in the public documentation examined.

The EIB approved its financing after the Saipem contract had already been signed.

Consequently, the bank should be able to explain what procurement evidence it reviewed during its appraisal.


8. The EIB’s procurement responsibilities

The EIB’s official project summary identifies ENI as a private-sector promoter not subject to European public procurement or concessions rules.

This classification means that the project is not automatically subject to the same tendering obligations as a conventional public-sector construction project.

However, the absence of an obligation to organise a public tender does not mean that procurement conditions are irrelevant to the EIB.

The bank’s March 2024 Guide to Procurement contains provisions concerning private-sector operations within the European Union.

Section 2.2 addresses the need for economically justified procurement procedures, competitive pricing and impartial commercial negotiations.

The relevant question is therefore not simply whether ENI was legally obliged to organise a public tender.

It is whether the EIB adequately established that the procurement arrangements were economically justified and that the prices were competitive.

That distinction is particularly significant when a substantial construction contract is awarded to a jointly controlled company.

The bank’s procurement guide also contains specific provisions addressing certain contracts involving affiliated companies outside the European Union. Those provisions should not be presented as automatically applicable to Livorno, which is situated within the EU.

Nevertheless, the more general private-sector procurement principles remain relevant.

The EIB should disclose the procurement approach approved for Livorno, the independent evidence supporting the contract prices, and the procedures used to evaluate potential conflicts of interest.

If independent bids were obtained, their existence and the evaluation criteria should be verifiable.

If the contract was negotiated directly, the economic justification for that procedure and the supporting market benchmarks should be identifiable.

In either case, the public-interest issue is whether the bank protected the economic integrity of the investment it agreed to finance.

Saipem’s previous international corruption proceedings

The historical compliance record of a principal contractor is another relevant consideration for institutional due diligence.

In 2010, the US Department of Justice announced that Snamprogetti Netherlands, a company then within the Saipem group and formerly owned directly by ENI, had agreed to a $240 million criminal penalty under a deferred prosecution agreement concerning bribery in the award of engineering and construction contracts in Nigeria.

Separately, in April 2020, the US Securities and Exchange Commission announced a $24.5 million settlement with ENI concerning accounting and internal control violations associated with historical improper payments by Saipem in Algeria.

ENI entered the settlement without admitting or denying the SEC’s findings.

The judicial outcome in Italy must also be stated: Saipem was definitively acquitted in the Italian Algeria proceedings in December 2020, following the rejection of the prosecution’s appeal.

These historical proceedings are unrelated to the Livorno contract.

They do not establish that present management or current contractors engaged in misconduct at Livorno.

Their relevance is more limited and specific: did the EIB’s integrity assessment consider the historical compliance record of the principal contractors and the safeguards applicable to this related-party transaction?

The EIB has established integrity and anti-fraud mechanisms capable of examining procurement, ownership arrangements and financial transactions.

Whether Livorno was subjected to an enhanced or proactive integrity review is not established by the public records examined for this investigation.


9. Construction delays and increasing contract values

The financial documentation of the hydrogen plant contractor provides unusually useful information concerning the project’s construction progress.

KT – Kinetics Technology, a subsidiary of MAIRE, signed its engineering, procurement and construction contract with ENI on 19 February 2024.

The installation is designed to produce hydrogen using steam reforming technology, with a nominal capacity of 32,000 normal cubic metres per hour.

MAIRE’s 2025 annual financial report identifies an original contract value of €123.8 million and contractual changes worth €11.55 million, bringing the full-life contract value to €134.85 million.

Its subsequent half-year 2026 reporting identifies a further revised contract value of €136.2 million.

Hydrogen production plantAmount
Original contract€123.8 million
Revised value at end of 2025€134.85 million
Revised value at June 2026€136.2 million
Increase from original value€12.4 million
Percentage increaseApproximately 10%

The 2025 annual report places the hydrogen plant’s readiness for commissioning-related activities in February 2027, provisional acceptance in August 2027 and final acceptance in August 2029.

Physical progress reported by MAIRE also illustrates the difference between overall project progress and actual construction progress.

Hydrogen plant progressDecember 2025June 2026
Overall physical progress60.0%76.2%
Construction or construction and precommissioning progress9.8%46.8%

The reported construction categories are not entirely identical between periods, but the figures provide a useful indication of the work remaining.

Saipem’s original annual report disclosure envisaged completion of its contracted activities during the third quarter of 2026.

By June 2026, reporting on the overall Livorno project identified an anticipated completion of construction by the end of 2026, followed by start-up during the first months of 2027.

The different contractual milestones should not be conflated.

Mechanical completion, readiness for commissioning, commercial start-up, provisional acceptance and full production are separate stages in industrial project development.

Nonetheless, the available information demonstrates that the anticipated industrial timetable has evolved.

The precise reasons for the contractual changes and schedule revisions remain unclear.

Were the changes caused by environmental permitting, engineering modifications, procurement difficulties, construction productivity or other factors?

Did previously unidentified conditions at the industrial site contribute?

How much has the overall project budget increased since the EIB’s approval?

Has the EIB reviewed the revised timetable and updated financial requirements?

And has the bank reconsidered the timing of the economic and environmental benefits originally projected?

A project’s financial returns and avoided emissions are affected by when it begins operating and how quickly it reaches its planned capacity.

Construction delays are therefore not simply an engineering issue. They can affect the original investment appraisal.


10. A biorefinery on a historically contaminated industrial site

One of the most important findings of this investigation concerns the environmental history of Livorno.

The refinery occupies land within a Sito di Interesse Nazionale, or SIN: an area designated by the Italian authorities for environmental remediation of national importance.

The Livorno SIN was established under legislation dating to 1998, with its original boundaries defined in 2003.

The refinery site has been subject to environmental characterisation, soil and groundwater risk assessments, monitoring and containment measures.

A parliamentary question submitted in July 2018 identifies historical contamination involving, among other substances:

  • Petroleum hydrocarbons.
  • Aromatic compounds.
  • Heavy metals, including lead.
  • Methyl tert-butyl ether, or MTBE.
  • Chlorinated organic compounds.
  • Fluorides.

The parliamentary question also raised concerns about odour emissions, air quality monitoring and the health of nearby communities.

These issues predate the biorefinery project.

The conversion of a conventional refinery into a renewable fuel installation does not automatically resolve environmental liabilities accumulated over decades of petroleum processing.

The distinction between remediation and containment is especially important.

A groundwater barrier can reduce the migration of pollutants and allow contaminated water to be extracted and treated.

Its operation does not necessarily establish that the underlying contamination has disappeared.

ENI’s answers to shareholders in 2026 confirm that an operational hydraulic barrier remains in place at Livorno, with extracted groundwater undergoing treatment on-site.

The same document confirms that ENI Rewind managed approximately 180,000 tonnes of material during the conversion, predominantly excavated soil and rocks.

The material was transferred to external recovery or disposal installations.

The reported expenditure was approximately €40 million, including €33 million during 2025.

The disclosure does not establish that all 180,000 tonnes consisted of hazardous or contaminated material. Excavated construction soil can require management for different reasons.

Nevertheless, the scale and cost of these activities demonstrate that soil management is a material component of the industrial conversion.

What proportion of the excavated material was contaminated?

Which treatment and disposal facilities received it?

What historical environmental liabilities remain?

Who bears the costs of managing those liabilities?

And were any of these expenditures included in the costs eligible for EIB financing?

These questions deserve a detailed answer.

The polluter-pays principle

The financial treatment of historical pollution must be distinguished from the financing of new industrial development.

In principle, the polluter-pays principle requires those responsible for environmental damage to bear the relevant costs, subject to the applicable legal framework.

Public financing of an industrial conversion is not automatically incompatible with that principle. Nor does a loan used for eligible environmental improvements necessarily amount to transferring pollution liabilities to taxpayers.

However, it is important to establish which costs relate to historical pollution and which relate to the development of the new biorefinery.

An Italian Senate response published before the EIB financing explains that the revised SIN boundaries excluded public areas and retained privately owned industrial land.

As a consequence, €869,199.79 in remaining national remediation programme resources could no longer be allocated to remediation interventions at the site.

There is no evidence that the EIB loan replaced those particular resources.

The episode nevertheless illustrates the importance of distinguishing public environmental expenditure from the liabilities of private industrial operators.

Has the EIB made that distinction in its appraisal of Livorno?


11. Previous criminal investigations concerning Livorno

The Livorno refinery has also been associated with previous criminal proceedings.

These cases must be described with their judicial outcomes and without suggesting that historical allegations establish wrongdoing in the present biorefinery project.

Fuel theft and excise-related proceedings

Italian judicial proceedings and press reports have documented investigations into fuel theft and alleged irregularities involving fuel distribution at the refinery.

In February 2019, Il Tirreno reported first-instance convictions involving numerous drivers and other individuals in a case concerning the misappropriation of fuel from the site.

The final outcome of subsequent appeals in that particular case has not been independently established for this investigation.

ENI’s financial disclosures also describe separate excise-related proceedings involving employees and former employees.

Those proceedings in Rome concluded in January 2023 with acquittal and limitation-related outcomes as reported by ENI. The company was identified as an injured party in the relevant case.

The different proceedings should not be merged into a single accusation.

Workplace safety proceedings

ENI’s financial reports identify a criminal proceeding concerning a workplace accident at the Livorno refinery in 2019, in which two employees were injured.

ENI was notified of the investigation in October 2020.

In March 2024, the company and the accused individuals were acquitted. According to ENI’s subsequent disclosure, the prosecution did not appeal and the decision became final.

Environmental criminal investigation

A report published by the judicial authorities in Florence in October 2023 identifies criminal proceeding No. 2565/2021 RGNR.

The proceeding concerned possible environmental and atmospheric pollution in the industrial area of Stagno, specifically referring to the ENI refinery.

At the time of that report, an evidentiary procedure was underway before the investigating judge.

The current status and final outcome of this proceeding have not been established for this article.

The existence of an investigation is not a finding of guilt.

Nevertheless, its existence before the EIB financing decision raises an appropriate institutional question.

Was the EIB informed of the environmental criminal proceeding?

Did the bank examine the underlying environmental issues, independently of whether the investigation ultimately resulted in charges or convictions?

Organised crime

No verified evidence has been identified establishing a direct Mafia connection to the Livorno biorefinery financing or construction contracts.

This investigation therefore does not allege such a connection.

Historical criminal investigations in the wider Livorno industrial or waste management sector cannot be attributed to ENI or its contractors without evidence of their involvement.


12. What did the EIB’s environmental assessment actually examine?

The European Investment Bank’s Environmental and Social Data Sheet for Livorno is dated 24 June 2025.

The three-page document provides a summary of the bank’s environmental and social assessment.

It addresses the planned production capacity, anticipated feedstock categories, environmental permitting, public consultations, greenhouse gas emissions and ENI’s environmental management systems.

It also acknowledges the environmental compatibility decision issued by the Italian authorities on 6 September 2024.

The document records that public consultations occurred and that additional information was requested during the Italian environmental assessment procedure.

It refers to a positive opinion issued by Italy’s public health institute, the Istituto Superiore di Sanità, in May 2024.

These are relevant safeguards and should not be overlooked.

However, the EIB’s published environmental summary does not explicitly discuss:

  • The refinery’s designation as part of a national remediation site.
  • Historical soil and groundwater contamination.
  • The continuing operation of groundwater containment infrastructure.
  • Outstanding historical environmental liabilities.
  • Potential allocation of historical remediation expenditure to the investment budget.
  • The environmental criminal investigation identified in the October 2023 judicial report.

The omission does not demonstrate that the bank ignored these matters during its internal appraisal.

A public data sheet is a summary rather than the entire body of technical due diligence.

Nevertheless, the environmental history of the site appears sufficiently material to warrant explicit explanation.

The final page of the assessment is particularly notable.

Under the heading concerning conditions for disbursement, the EIB states:

“None.”

The document does, however, require ENI to notify the bank of subsequent modifications capable of triggering environmental permitting procedures.

ENI has also confirmed in its 2026 shareholder answers that the financing agreements contain environmental, social, health and safety, legal compliance and management obligations.

It would therefore be incorrect to conclude that the EIB imposed no environmental requirements whatsoever.

The narrower and more important question is why no specific environmental condition precedent to disbursement was identified in the public assessment.

Given the documented historical contamination, was any environmental milestone required before financing became available?

Was the status of remediation independently assessed?

Did the bank verify whether the proposed construction areas were environmentally suitable for their intended industrial use?

What monitoring, reporting and corrective action obligations were incorporated into the full financing agreement?

The EIB should provide the underlying appraisal or an appropriately redacted version sufficient to explain its conclusions.


13. Environmental authorisations are still evolving

The original Livorno project received a positive environmental compatibility decision from Italy’s Ministry of Environment and Energy Security on 6 September 2024.

That approval is an important part of the institutional record.

However, the environmental procedures did not end there.

The Italian government’s environmental assessment portal identifies subsequent procedures concerning compliance with prescribed environmental requirements and modifications to the project.

Among them:

ProcedureDate submittedStatus recorded in the portal when examined
Updated Livorno biorefinery project, No. 1475316 March 2026Decision being prepared
Verification of compliance with specified requirements23 September 2026Awaiting another administration’s opinion

The updated project documentation was republished for further public consultation in July 2026.

Documents associated with that procedure identify, among other changes, a proposed second acid gas treatment unit.

Other compliance procedures have been completed successfully. The existence of pending procedures does not mean that the original project was entirely unauthorised.

Nor does it automatically establish that construction or commissioning cannot proceed.

However, the evolution of the project raises questions about the EIB’s ongoing monitoring responsibilities.

The bank’s environmental assessment expressly requires notification of qualifying project modifications.

Has ENI notified the EIB of the 2026 changes?

Has the bank assessed their effect on construction costs, operational emissions and the original commissioning timetable?

Does the revised design alter the projected energy consumption or environmental performance?

Has the EIB requested an updated carbon footprint calculation?

A financing decision based on an industrial design should be capable of responding to material changes in that design.


14. The 530,000-tonne feedstock question

At planned capacity, the Livorno biorefinery is expected to process approximately 530,000 tonnes of biological feedstock annually.

That represents an indicative average of more than 44,000 tonnes per month.

The EIB envisages a feedstock mix consisting mainly of fatty residues, including used cooking oil, animal fats and industrial residues, together with a smaller agricultural component presenting a low risk of indirect land-use change.

The environmental and economic performance of the facility will depend heavily on the availability, characteristics, price and origin of these materials.

The scale of the procurement requirement is substantial.

ENI is not merely developing Livorno. Its strategy also involves existing Italian biorefineries, additional conversions and international capacity expansion.

These facilities may compete for some of the same raw materials.

Scarcity of genuinely sustainable waste oils and fats could increase prices or encourage the use of substitute feedstocks.

A new production facility cannot be assessed independently of the raw material market required to sustain it.

In its 2026 answers to shareholders, ENI was specifically asked about the geographical origin and percentage composition of Livorno’s future feedstock.

The company explained that its anticipated allocation assumed a distribution comparable to that of its two existing biorefineries.

This is an important distinction between an anticipated sourcing model and disclosed Livorno-specific contractual commitments.

The answer does not establish that ENI lacks supply agreements.

It does, however, leave unanswered the precise geographical and quantitative composition of Livorno’s future raw material supply.

What Tuscany’s environmental agency already knew

A technical assessment by Tuscany’s environmental protection agency, ARPAT, provides additional information.

The agency identifies anticipated potential geographical origins for biological feedstock associated with the Livorno project.

Feedstock categoryIndicative geographical origins identified
Residual animal fatsEurope
Used oils from the food industryEurope and the Far East
Vegetable oilsEurope, Asia, the Middle East and Africa
Vegetable-based industrial residues and co-productsEurope, the Middle East, the Far East and South America

The assessment also indicates that maritime transport would play a major role in feedstock deliveries, using existing petroleum port infrastructure connected to the refinery by pipelines.

These are indicative geographical categories, not evidence of actual purchases from specific countries.

ARPAT also considered it appropriate for ENI to favour locally sourced materials.

That recommendation deserves particular attention given the potentially global nature of the supply chain.

Was a predominantly local or European sourcing scenario examined?

Was such a scenario commercially viable?

How much feedstock can realistically be obtained from Italy?

What happens if European demand for waste oils increases faster than their availability?

What assumptions concerning imported feedstock were incorporated into the EIB’s assessment?

The bank’s environmental calculations cannot be independently evaluated without understanding these variables.


15. Used cooking oil and the risk of feedstock fraud

Used cooking oil has become an important raw material for the European biofuel industry.

Its commercial attraction derives partly from its classification as waste and the associated advantages under renewable energy legislation.

However, the distinction between genuine used cooking oil and virgin vegetable oil declared as waste is economically significant.

A system that offers greater commercial value to waste-derived oils creates incentives for accurate classification, but also potential incentives for fraudulent classification.

In July 2025, the European Commission published the results of an examination of suspected fraud involving biodiesel imports from China.

German authorities had notified the Commission of the allegations in March 2023.

On 18 July 2025, the Commission stated that it had identified systemic weaknesses in the conduct of certain certification audits.

It also explicitly stated that the information collected had not allowed it to confirm the alleged fraud.

The timing is relevant.

The EIB approved the Livorno financing on 24 June 2025.

The Commission published its findings on 18 July.

The EIB’s register records the financing signature on 23 July.

The EIB’s environmental assessment relies on EU-recognised voluntary certification schemes to substantiate compliance with renewable energy sustainability criteria.

Did the bank consider the weaknesses identified by the Commission before concluding the financing agreement?

Did it require enhanced verification of feedstock origin?

Will Livorno receive used cooking oil originating in China or other Far Eastern markets?

If so, which suppliers and certification organisations will be involved?

What safeguards will be used to detect blending of genuine waste oils with virgin vegetable oils?

Certification remains an important regulatory instrument. But a certificate is only as reliable as the data, inspections, traceability systems and enforcement mechanisms supporting it.

There is no evidence presented here establishing that Livorno will receive fraudulently classified Chinese feedstock.

The concern is whether the project’s risk assessment adequately addresses vulnerabilities already identified at sector level.


16. Africa: the agricultural side of ENI’s biofuel strategy

ENI’s renewable fuel strategy extends beyond industrial refining.

The group is developing agricultural supply chains through dedicated businesses and partnerships involving farmers, commercial intermediaries, processing installations and international financial institutions.

The business model seeks to produce vegetable oils for export to ENI’s biorefineries.

In May 2024, the International Finance Corporation, part of the World Bank Group, and the Italian Climate Fund announced a $210 million financing package supporting ENI’s agricultural activities in Kenya.

Financing institutionAnnounced amount
International Finance Corporation$135 million
Italian Climate Fund$75 million
Total$210 million

The programme was presented as supporting agricultural development, renewable fuel production and the livelihoods of up to 200,000 Kenyan farmers.

It involves contractual relationships with farmers and agricultural aggregators supplying oilseeds to ENI’s processing facilities.

The extracted vegetable oils are intended for export to Italian biorefineries.

The Italian Climate Fund is managed by Cassa Depositi e Prestiti.

This creates another documented institutional connection within the wider financial ecosystem surrounding ENI’s activities.

CDP is a significant shareholder in ENI, participates through CDP Equity in the joint control of Saipem, and manages the Italian Climate Fund involved in financing ENI’s Kenyan agricultural strategy.

These relationships are not evidence of misconduct. They reflect the considerable institutional role of Italian public financial entities in industrial development.

However, their cumulative economic contribution to ENI’s biofuel strategy deserves examination.

The financial structure encompasses development lending in Africa, corporate investment in Europe and public-bank financing for refinery conversions.

The individual financing operations have distinct purposes and legal structures. Their amounts cannot simply be added together and described as subsidies for Livorno.

Nevertheless, the economic relationship between feedstock production and biofuel manufacturing makes it appropriate to examine the wider industrial system.

Agricultural production and food markets

In November 2021, ENI announced a strategic partnership with the Italian agricultural group BF, associated with Bonifiche Ferraresi.

The stated purpose included research and development of agricultural products suitable for biofuel production, including potential cultivation in Italy and abroad.

The initiative also involved equity investments.

BF is a diversified agricultural group rather than a business exclusively dedicated to renewable energy.

This raises broader questions about the relationship between ENI’s agricultural strategy, food markets, livestock feed and fuel production.

The extraction of vegetable oil from oilseeds generates additional products, including residual agricultural material that may have commercial value in animal feed markets.

An integrated agricultural business can therefore generate revenues beyond the sale of vegetable oils to biorefineries.

Such integration can improve resource efficiency and contribute to commercial viability.

It can also complicate the assessment of land-use competition and the allocation of environmental benefits between products.

Which agricultural activities are exclusively dedicated to biofuel feedstock?

Which activities generate revenue from food, animal feed or fertiliser markets?

Who receives those revenues?

How are agricultural land use, energy consumption and greenhouse gas emissions allocated between the various products?

And how much public financing supports activities that ultimately supply European biofuel manufacturing?

These are questions about the commercial architecture of the agricultural strategy, not allegations against farmers or agricultural businesses.


17. South Africa, Kenya and Italy: a complicated supply chain

An investigation published by Transport & Environment on 31 March 2026, drawing on trade records and work by SourceMaterial, identified substantial imports of South African rapeseed into Kenya by ENI-related businesses.

The South African supplier identified in the trade records was Southern Oil Pty Limited.

The investigation reported maritime shipments of rapeseed to Kenya, where the seeds could be processed before the resulting vegetable oil was exported to Italy.

Transport & Environment estimated that rapeseed represented a potentially very large proportion of the Kenyan feedstock exports.

ENI disputes the estimate of approximately 80%.

In its own subsequent explanations, ENI stated that rapeseed accounted for approximately 40% of the oilseed feedstock volumes exported from Kenya in 2025.

ENI maintains that imports complement its local agricultural operations and that the processing activities also support the animal feed sector.

The competing interpretations concern the scale, purpose and performance of the Kenyan agricultural programme.

The existence of South African imports is no longer merely an external allegation. ENI has acknowledged them.

The potential supply chain is therefore considerably more complex than a simple relationship between Kenyan farmers and Italian biofuel consumers.

It can involve:

  1. Cultivation and harvesting in South Africa.
  2. Transport to South African ports.
  3. Maritime transportation to Kenya.
  4. Inland transportation and processing in Kenya.
  5. Vegetable oil extraction.
  6. Maritime export to Italy.
  7. Further transportation, storage and industrial refining.

A considerable amount of economic activity and energy consumption occurs before the vegetable oil reaches an Italian biorefinery.

The obvious question is why South African oilseeds are transported to Kenya for processing instead of being processed closer to their place of cultivation and shipped directly to their final industrial market.

There may be legitimate reasons involving processing capacity, animal feed demand, existing contractual commitments and industrial infrastructure.

Those reasons should be explained and quantified.

Long-distance maritime transportation does not automatically make a biofuel more carbon-intensive than its fossil equivalent. Bulk maritime freight can be relatively efficient per tonne transported.

But the environmental consequences of the actual logistics must be measured rather than assumed.

How much fuel is consumed by inland transportation?

What are the maritime distances and shipping emissions?

How much energy is required for processing and oil extraction?

How are emissions allocated between vegetable oil and animal feed?

Were alternative sourcing and processing arrangements evaluated?

The existence of this supply chain is relevant to ENI’s overall renewable fuel strategy.

No contractual evidence has yet been identified establishing that South African rapeseed processed in Kenya will specifically supply the Livorno biorefinery.

That distinction is essential.


18. The missing connection: compostable plastics

Until now, the Livorno project has largely been presented as an energy transition investment.

However, examining the wider ENI industrial ecosystem introduces another potentially important component: compostable plastics and their end-of-life treatment.

On 18 October 2023, Versalis announced that it had completed its acquisition of the remaining shares in Novamont, obtaining full ownership of the company.

Novamont is a major producer of biodegradable and compostable plastics, including materials used in bags, food packaging and agricultural applications.

Through Versalis, Novamont forms part of the ENI group.

ENI also operates in environmental remediation and waste management through ENI Rewind.

The group is simultaneously expanding renewable fuel production through its biorefining activities.

These businesses occupy different positions within the industrial value chain.

ENI-related businessPrincipal activity relevant to this investigation
Versalis and NovamontProduction of chemicals and compostable plastics
ENI RewindEnvironmental remediation and waste management
ENI Natural EnergiesAgricultural feedstock development
ENI and EniliveBiofuel production and distribution
SaipemEngineering and construction of industrial infrastructure

Their coexistence within the same corporate ecosystem creates the potential for industrial integration.

The question is what form such integration actually takes.

Does ENI’s involvement in waste treatment provide alternative outlets for materials produced by its chemical businesses?

Can organic waste processing contribute to renewable energy production?

Could residues from composting facilities enter thermal conversion installations?

And how would the environmental performance and circularity of such a system be measured?

These questions become particularly relevant when examining historical proposals associated with the Livorno refinery site.


19. Waste-to-chemicals: the ENI–ALIA project

In July 2019, the Tuscany Region approved a proposed cooperation protocol involving ENI and ALIA Servizi Ambientali.

The agreement concerned the development of a waste-to-chemicals installation associated with the Livorno refinery.

The proposed technology involved high-temperature conversion of waste into synthesis gas, with the possibility of manufacturing methanol.

Official regional documentation envisaged a processing capacity in the range of approximately 170,000 to 200,000 tonnes of waste annually.

The project contemplated industrial synergies with the existing refinery.

Most significantly, the documents identify potential waste streams including rejects generated through the sorting of separately collected plastics and the composting of organic materials.

That is an important documented finding.

It establishes that composting rejects were contemplated as a potential feedstock for the proposed thermal conversion project.

It does not establish that those rejects consisted specifically of Novamont’s compostable plastics.

Organic waste treatment facilities can generate different types of rejects, including conventional plastics, other contaminants and material that has not sufficiently decomposed.

The composition and origin of the intended waste streams would therefore need to be established through waste classification, characterisation and commercial agreements.

The proposed project also involved the possible creation of a dedicated business entity.

Who would own that entity?

Who would supply its waste?

Would it receive gate fees for accepting waste?

Who would purchase the methanol?

Would its products be classified as chemical feedstock or fuel?

Would it receive public support?

These questions are relevant to the project’s commercial and environmental justification.

Has the gasification facility actually been built?

Here an important qualification is necessary.

A technical report prepared by ARPAT during examination of Tuscany’s waste planning documents states that the ENI Rewind waste-to-chemicals project had been announced in 2019, but the agency was not aware of a corresponding permitting procedure having been initiated at the time of its assessment.

The existence of a proposal must therefore not be confused with the existence of an operational installation.

Bioplastics News has not established that the gasification facility was constructed, commissioned or connected to the EIB-financed biorefinery.

Nor has it established whether the original proposal has subsequently been abandoned, postponed, replaced or incorporated into another industrial development.

This distinction substantially affects the interpretation of the Livorno industrial ecosystem.

The official proposal is relevant evidence of a contemplated industrial strategy. It is not evidence of actual waste processing.


20. Waste-to-gas: the biomethanization proposal

Tuscan planning documents also identify a separate ENI Rewind proposal involving anaerobic digestion of organic waste at Livorno.

The project has been described as a waste-to-gas installation, intended to produce biomethane from organic and green waste.

Anaerobic digestion uses microorganisms to break down suitable organic materials in the absence of oxygen.

The process generates biogas, which generally contains methane and carbon dioxide.

After purification and upgrading, the methane component can be used as biomethane.

Potential applications include injection into the natural gas distribution network, industrial energy consumption or transport fuel.

The process also generates digestate, which may have agricultural value if it meets appropriate quality and environmental requirements.

The commercial attraction of biomethanization is therefore potentially twofold: waste treatment and energy production.

Once again, the distinction between proposed infrastructure and operational infrastructure is essential.

The ARPAT technical report identified the ENI Rewind anaerobic digestion proposal but stated that it had no further information about the development at the time.

It also identified an additional potential waste-to-fuel proposal for organic waste.

Consequently, we cannot assume that any of these installations currently operates at Livorno.

Their future status, ownership, permitted feedstocks and relationships with the biorefinery should be clarified.

In particular, we need to establish whether compostable plastic packaging or rejects from organic waste treatment facilities were contemplated as feedstock.

Certification for industrial compostability does not automatically establish compatibility with the specific conditions and retention times of commercial anaerobic digestion facilities.

Some compostable materials may biodegrade insufficiently during digestion. Others may require subsequent aerobic treatment.

Without reliable measurements, the destination of those materials cannot be inferred from the name of the treatment process.


21. Hydrogen: the potential industrial link

The Livorno biorefinery includes a hydrogen production installation using methane-based steam reforming.

Methane is converted through industrial chemical processes into hydrogen, with associated carbon dioxide generation.

The hydrogen is subsequently required for the conversion of vegetable oils and fats into renewable fuels.

This creates a potential connection between biomethanization and biofuel production.

Once sufficiently purified, biomethane is chemically equivalent to fossil methane.

In principle, renewable methane can therefore substitute for fossil methane as an input to compatible steam reforming installations.

Gasification creates another potential route.

The synthesis gas generated by gasification generally contains hydrogen, carbon monoxide and other compounds.

Depending on the plant design, synthesis gas can be processed to recover hydrogen or used to manufacture chemicals such as methanol.

Methanol can itself be converted into hydrogen through a separate reforming process.

These potential pathways can be represented as follows:

Pathway 1 — Biomethanization

Organic waste → Anaerobic digestion → Biogas upgrading → Biomethane → Methane reforming → Hydrogen → Biofuel production

Pathway 2 — Gasification

Suitable waste → Gasification → Synthesis gas → Gas treatment and hydrogen recovery → Potential industrial hydrogen use

Pathway 3 — Gasification and chemical production

Suitable waste → Gasification → Synthesis gas → Methanol → Fuel or chemical applications

The three pathways are technically different.

The Livorno methane reformer should not be assumed capable of directly accepting methanol or untreated synthesis gas.

Such applications would require appropriate equipment, process design, purification and industrial integration.

The relevant question is whether any of these relationships were incorporated into ENI’s actual industrial strategy for the Livorno site.

Were the historical waste projects intended to supply biomethane, hydrogen or other chemical resources to the refinery?

Were common utilities or interconnecting infrastructure planned?

Could the installations generate economic synergies across ENI’s chemicals, waste management and biofuel businesses?

Were those potential synergies incorporated into the EIB’s financial or environmental appraisal?

There is currently insufficient evidence to establish that these pathways operate as an integrated system in Livorno.

Their technical feasibility and the official waste treatment proposals nevertheless justify further investigation.


22. Organic recycling: what does the term actually mean?

One of the most interesting aspects of the compostable plastics debate concerns terminology.

The industry increasingly describes the treatment of compostable packaging using the term organic recycling.

Unlike conventional plastic recycling, organic recycling does not necessarily involve the recovery of the original polymer or the production of another plastic article.

The term has a historical legal basis in European packaging legislation and includes biological treatment processes such as composting and biomethanization under applicable conditions.

It is not a newly invented term.

However, its meaning can be misunderstood.

Consumers may reasonably associate compostable packaging with the production of compost and the return of organic material to agricultural soil.

The biological fate of the packaging material itself is more complicated.

During successful aerobic biodegradation, much of the carbon contained in a compostable polymer is converted into carbon dioxide.

Other carbon may become incorporated into microbial biomass or residual organic matter.

The original plastic polymer is not necessarily recovered as a new useful material.

The European Environment Agency acknowledges that compostable plastics do not contribute nutrient value to compost. Their principal potential benefit lies in facilitating the collection and management of organic waste.

This distinction is important.

A product can potentially support the separate collection of food waste without itself providing agronomic benefits.

The environmental justification for using compostable packaging should therefore be based on demonstrated improvements in the overall waste management system rather than an assumption that the packaging enriches the soil.

Commercial operating conditions

Laboratory compostability certification establishes performance under defined testing conditions.

Commercial treatment facilities operate under practical constraints involving throughput, retention time, contamination levels, temperature, moisture and economic requirements.

A certified compostable plastic may not completely biodegrade within the actual operating cycle of every treatment installation.

Depending on the facility and product, material may be removed during screening, remain in intermediate treatment streams or enter subsequent treatment processes.

The scale of these outcomes must be established through independent measurements.

Neither universal failure nor universal success can reasonably be assumed.

The key question is how much compostable packaging placed on the Italian market actually completes the treatment process for which it was designed.


23. Recycling statistics and the destination of compostable plastic waste

The Italian consortium BIOREPACK reported a recycling rate of 57.8% for compostable plastic packaging in 2024.

Such figures are important to the environmental and regulatory justification of the compostable packaging market.

However, understanding what a recycling rate represents requires examination of the underlying methodology.

What quantity of compostable packaging was placed on the market?

How much was separately collected?

How much entered organic waste treatment installations?

How much was removed before biological treatment?

How much remained undegraded after treatment?

How much was sent for disposal or energy recovery?

These distinctions are not merely semantic.

Eurostat’s guidance on reporting packaging waste explicitly requires exclusions for biodegradable packaging removed before, during or after the recycling operation.

It also explains that compostable packaging residues subsequently sent for thermal treatment, including pyrolysis and gasification in the relevant circumstances, are not to be counted as recycled.

Anaerobic digestion presents a more complicated situation.

Where digestion generates a qualifying digestate or another recycled material, the eligible input may count towards recycling subject to the relevant rules and deductions for rejects.

The production of methane does not, by itself, make all the input material recyclable for statistical purposes.

Gasification is not organic recycling. Its regulatory classification depends partly on the nature and ultimate use of the resulting products.

Conversion of waste into a fuel does not constitute material recycling merely because an intermediate chemical resource has been produced.

These distinctions are particularly relevant to the historical Livorno gasification proposal, which explicitly envisaged processing rejects from composting facilities.

If such rejects include compostable packaging, the destination of that material should be identifiable in waste accounting.

Was it biologically recycled?

Was it converted into fuel?

Was it processed into a chemical used for material production?

Was it incinerated?

Was it sent for another disposal operation?

An industrial process may have legitimate environmental advantages over an alternative waste treatment route without qualifying as recycling.

The problem would arise if different treatment outcomes were represented as equivalent for statistical or commercial purposes when applicable rules require them to be distinguished.

No evidence has been established that BIOREPACK or ENI has improperly counted Livorno-related waste as recycled.

The question is whether sufficient independent data exists to verify the reported figures and the actual fate of compostable packaging.


24. The biorefinery itself will generate substantial waste

Discussion of renewable fuels often focuses on the industrial use of waste as raw material.

Less attention is given to the waste generated by the production process itself.

ARPAT’s assessment identifies an estimated annual waste production from the new biological refining sections of approximately 79,318 tonnes.

This includes:

Estimated waste categoryAnnual quantity
Hazardous wasteApproximately 4,216 tonnes
Non-hazardous wasteApproximately 75,103 tonnes
TotalApproximately 79,318 tonnes

The figures are estimates presented in environmental planning documentation, not actual measured operational results.

The assessment identifies potential recovery routes involving biological treatment and other processes for extracting or recovering valuable materials.

It also refers to possible use of third-party treatment installations outside Tuscany.

This introduces another dimension to the project’s logistics and environmental accounting.

A facility intended to valorise waste and biological residues will itself generate substantial waste streams.

Where will those waste streams be transported?

Which companies will treat them?

What proportion will be recovered, incinerated or disposed of?

What revenues or disposal costs will arise?

How much additional transportation will be required?

Will any of the historical ENI Rewind waste treatment proposals eventually handle these materials?

These are relevant questions for the project’s operating costs, environmental impact and industrial integration.

It is insufficient to count the amount of waste entering the biorefinery without also examining what leaves it.


25. The real economics of the circular economy

The Livorno case provides an opportunity to examine the wider commercial incentives surrounding the circular economy.

An integrated industrial group operating in chemicals, agriculture, waste management and renewable fuels may potentially benefit from several revenue streams.

These include:

  • Selling higher-value products marketed on environmental characteristics.
  • Processing waste and receiving treatment revenues where applicable.
  • Selling recovered energy or chemicals.
  • Benefiting from regulatory demand for renewable fuels.
  • Accessing public development financing, subsidies or investment incentives where available.
  • Attracting private investment through anticipated growth and sustainability objectives.

There is nothing intrinsically improper about combining these activities.

A well-designed integrated industrial system may use resources more efficiently than separate installations operating independently.

However, the existence of multiple revenue streams does not itself establish environmental or economic efficiency.

The system must be examined through four distinct balances.

The mass balance

Where does each tonne of input material end up?

In the case of compostable plastics, this means distinguishing biodegraded material, gaseous emissions, microbial biomass, residues, recovered products and discarded material.

In the case of biofuels, it means accounting for feedstock, hydrogen, final fuels, co-products and process waste.

The energy balance

How much energy is consumed in cultivation, harvesting, transportation, processing, purification, waste treatment and final refining?

How much usable energy is recovered?

If a particular waste conversion pathway consumes disproportionate quantities of energy relative to its outputs, its environmental and industrial rationale should be explained.

However, the energy balance must also account for the function of the waste treatment process, displaced products and valuable co-products.

A negative energy balance for a narrowly defined fuel-production pathway does not necessarily mean that the entire waste management system has no environmental benefit.

No verified Livorno-specific study has been identified demonstrating that a proposed compostable-plastic-to-fuel pathway consumes more energy than the fuel it would produce.

The data required to assess that hypothesis remains unavailable.

The carbon balance

What is the total greenhouse gas impact of the system?

This includes direct emissions, electricity, natural gas, hydrogen, agricultural inputs, transportation, methane leakage and the consequences of alternative waste treatment methods.

The carbon balance must distinguish biological carbon from fossil carbon and apply appropriate lifecycle accounting methodologies.

The financial balance

Would the industrial system remain commercially viable without regulatory incentives and favourable public financing?

What return does it generate for its shareholders?

What portion of its profitability derives from underlying industrial efficiency, and what portion derives from policy-created markets?

A project can be profitable while having limited environmental benefits. Equally, it can provide environmental benefits that justify public intervention despite modest private financial returns.

The two questions must be assessed separately.

The challenge is to establish whether the commercial incentives and environmental objectives are genuinely aligned.


26. The EIB’s carbon footprint calculation

The EIB has estimated the annual greenhouse gas emissions of the Livorno biorefinery at approximately 738,600 tonnes of CO₂ equivalent.

It estimates annual avoided emissions of approximately 660,500 tonnes of CO₂ equivalent compared with a fossil fuel baseline.

The implied comparison is as follows:

Annual emissions scenarioTonnes CO₂ equivalent
Implied conventional fossil fuel baseline1,399,100
Livorno biorefinery scenario738,600
Estimated annual avoided emissions660,500
Indicative reduction against implied baseline47.2%

The fossil baseline and percentage reduction above are derived from the EIB’s published estimates.

The figures concern the bank’s project-level carbon accounting exercise. They should not be automatically equated with the lifecycle greenhouse gas savings thresholds used to certify individual renewable fuels under EU legislation.

This is an important distinction.

Nevertheless, the projected reduction is substantial and forms part of the environmental justification for the financing.

The EIB indicates that its calculation accounts for production processes, energy consumption, feedstock logistics and relevant indirect emissions.

The bank’s public environmental summary does not disclose the detailed quantitative assumptions supporting those estimates.

For example:

ParameterDetailed quantitative assumptions disclosed in the EIB environmental summary?
Feedstock mix by categoryNo
Feedstock mix by countryNo
Agricultural inputsNo
Inland transportation distancesNo
Maritime transportation routes and distancesNo
Oil extraction energy consumptionNo
Hydrogen production emissionsNo separate breakdown
Methane leakage assumptionsNo
Land-use-change assumptionsNo separate breakdown
Feedstock price and substitution scenariosNo
Sensitivity analysisNo
Uncertainty rangeNo

A project carbon footprint can legitimately be estimated before an industrial facility begins operating or before all supplier contracts have been concluded.

Such calculations frequently rely on representative scenarios, standard emission factors and forecasts.

Their usefulness depends on the quality of the assumptions and the treatment of uncertainty.

In Livorno’s case, the potentially worldwide feedstock supply chain makes the geographical assumptions particularly important.

A calculation based predominantly on European waste oils could yield different results from one incorporating substantial volumes of material originating in Africa, Asia or South America.

Different feedstocks also have different agricultural, processing and transportation impacts.

The use of fossil methane for hydrogen production introduces further variables.

How much natural gas will be consumed?

What emissions factor has been applied?

Has upstream methane leakage been considered?

Will the calculation change if biomethane is used?

Were alternative hydrogen production technologies examined?

Will any actual waste-to-gas or waste-to-chemicals integration be reflected in the carbon accounting?

Without the underlying calculation, the public cannot independently reproduce the EIB’s estimate.

This does not establish that the estimate is inaccurate.

It establishes that its accuracy cannot be independently verified from the published environmental summary alone.

The EIB should disclose its principal assumptions, methodology, sensitivity analysis and arrangements for monitoring actual emissions after the plant becomes operational.


27. Environmental benefits versus commercial viability

The Livorno investment is closely connected to European and Italian renewable energy policies.

Demand for hydrogenated biofuels is supported by regulatory obligations, decarbonisation targets and requirements concerning renewable fuels in transport.

The European Investment Bank identifies the Renewable Energy Directive, the European Green Deal and REPowerEU among the policy objectives supported by the project.

ENI also has established fuel distribution infrastructure through which biofuel products can potentially be marketed.

These are relevant commercial advantages.

However, there is a distinction between an anticipated market and committed demand.

Bioplastics News has not identified a complete set of Livorno-specific long-term purchasing agreements establishing the future sale of its production.

This does not mean that no customers exist.

ENI’s own distribution network and group purchasing arrangements may provide significant market outlets without requiring public disclosure of individual sales contracts.

Nevertheless, the economic foundations of the investment remain important.

What are the expected annual revenues?

What are the projected operating costs?

What is the anticipated return on invested capital?

What is the break-even capacity utilisation rate?

How sensitive is profitability to feedstock prices?

What would happen if natural gas prices increased?

How would lower-than-expected demand affect the investment?

What would happen if competing renewable fuel technologies became more commercially attractive?

The longer-term relationship between biofuels and electrification also deserves examination.

European transport decarbonisation involves several technological pathways, including electrification, renewable fuels and improvements in efficiency.

As these pathways evolve, the addressable market for different fuel products may change.

A 15-year financing agreement should be based on an industrial strategy capable of responding to that evolution.

The central issue is not whether biofuels will have a market.

It is whether the specific scale, cost and technological configuration of Livorno were appropriately assessed against plausible future market scenarios.


28. Who approved the €500 million financing?

The EIB’s official register identifies 24 June 2025 as the approval date for the Livorno financing.

An additional institutional document provides more information concerning the approval mechanism.

The bank’s register of decisions taken under delegated authority during June 2025 identifies the ENI biorefinery operation among the financing decisions approved through the Management Committee under authority delegated by the Board of Directors.

The use of delegated authority is an established institutional procedure.

It does not, in itself, indicate an attempt to bypass scrutiny.

Nevertheless, the procedure makes it appropriate to establish precisely who examined and recommended the operation.

Which members of the Management Committee participated?

Who presented the project?

Which EIB technical departments examined the industrial feasibility?

Who assessed the historical environmental liabilities?

Who examined the procurement arrangements and related-party transactions?

Who prepared or approved the carbon footprint calculation?

Were any objections or reservations recorded?

Were conflicts of interest declared and assessed?

Were any decision-makers excluded from particular deliberations?

The published register establishes the approval mechanism and the date.

It does not identify the complete individual decision-making chain or disclose the underlying deliberations.

The bank should provide sufficient information to clarify those responsibilities.

The European Commission also has an institutional role under the EIB’s statutory framework in relation to financing operations.

The relevant Commission opinion or assessment concerning Livorno, if available, would provide an additional source of information about the project’s compatibility with European policy and legislation.


29. Gelsomina Vigliotti, ENI and an institutional connection

The Livorno financing agreement was publicly signed by ENI CEO Claudio Descalzi and EIB Vice-President Gelsomina Vigliotti.

Vigliotti previously held senior positions within the Italian Ministry of Economy and Finance.

Her official EIB curriculum vitae also identifies her membership, since September 2023, of the governing body of the Istituto Affari Internazionali, known as IAI.

IAI is an Italian research institute and think tank examining international affairs, including energy policy.

Its own website identifies a strategic partnership with ENI dating from 2018.

The partnership involves research and discussion of energy-related economic, industrial, technological and political issues.

Vigliotti disclosed her IAI position in an official declaration of interests, indicating that it was unpaid.

The documented relationships can therefore be summarised as follows:

Entity or individualDocumented relationship
Gelsomina VigliottiEIB vice-president and signatory of the Livorno financing agreement
Gelsomina VigliottiDisclosed unpaid governing role at IAI
IAIStrategic institutional partnership with ENI
ENIBorrower and project promoter in the Livorno financing

These relationships do not establish an improper conflict of interest.

The position was publicly disclosed, and there is no evidence that Vigliotti received personal financial benefits from ENI through IAI.

A research partnership between a multinational company and a think tank is also not inherently improper.

Nevertheless, the overlap is relevant to institutional conflict-of-interest management.

Was the IAI–ENI strategic relationship considered in connection with the Livorno financing?

Did the EIB determine that no conflict existed?

Were any safeguards applied?

Did Vigliotti participate in the internal approval decision, or was her role limited to responsibilities associated with the agreement and its signature?

Signing a financing agreement does not, by itself, establish individual participation in every preceding appraisal or approval decision.

The relevant issue is whether the bank’s conflict-of-interest procedures were correctly applied and whether their application can be demonstrated.

No evidence of undisclosed family relationships, personal payments or corrupt conduct by Vigliotti has been identified for this investigation.


30. Why was the project documentation published after approval?

One of the most striking findings concerns the chronology of the EIB’s public documentation.

The EIB’s Transparency Policy generally provides for project summaries to be published at least three weeks before financing approval.

The policy allows exceptions where justified interests require delayed publication.

Those exceptions can, in certain circumstances, permit publication after approval or even after financing signature.

The existence of exceptions means that delayed publication is not automatically a violation of the bank’s policy.

Nevertheless, the Livorno chronology deserves examination.

DateEvent
24 June 2025EIB financing approved
24 June 2025Environmental and Social Data Sheet dated
23 July 2025Financing signature recorded in EIB project register
24 July 2025EIB–ENI financing publicly announced
25 July 2025Bioplastics News publishes its original critical article
31 July 2025Release date recorded for the EIB project summary
12 August 2025Environmental and Social Data Sheet published
4 September 2025June delegated approval decisions published

According to the dates displayed in the EIB’s public register, the project summary was released 37 days after financing approval.

It was also released after the financing signature.

Why?

Was an exception to the Transparency Policy requested?

If so, who requested it?

Was the request based on commercial confidentiality?

Which EIB authority approved delayed publication?

What was the justification?

Was any consideration given to publishing non-confidential information before approval?

The distinction between documentation existing internally and being publicly available is central to this investigation.

The environmental assessment was prepared before the publication of Bioplastics News’ original article, but its recorded public release occurred afterwards.

The journalist and the public could not necessarily examine the same body of information available to the EIB when the financing was approved.

A European Ombudsman precedent

In 2023, the European Ombudsman examined the EIB’s handling of an access request involving a project summary for an electricity distribution investment in Poland.

The inquiry concerned a project promoter’s request to postpone publication and the bank’s reliance on confidentiality considerations.

The Ombudsman questioned the adequacy of the reasoning supporting the EIB’s refusal to disclose the requested information and called for improvements in transparency practices.

The case did not concern ENI or Livorno.

It nevertheless demonstrates that exceptions to project disclosure can be subject to institutional scrutiny.

The Livorno operation raises a comparable transparency question: what justified publishing the recorded project summary only after the financing had been approved and signed?


31. ENI and the Paris Agreement

Another noteworthy passage appears in the EIB’s environmental assessment under its framework for assessing counterparties’ alignment with the Paris Agreement.

The bank acknowledges that ENI undertakes activities considered incompatible with the Paris Agreement under the relevant PATH assessment framework.

The EIB nevertheless concludes that ENI can receive support because the financing concerns renewable energy investment under REPowerEU and the applicable eligibility conditions are satisfied.

The assessment also considers ENI’s existing transition plans sufficient under the framework.

This is a documented policy-based eligibility decision.

It is not an admission that the financing was unlawful.

Nevertheless, it illustrates an important feature of contemporary climate finance.

A multinational corporation can undertake activities regarded as incompatible with climate objectives while simultaneously obtaining preferential public financing for selected renewable investments.

Whether that approach contributes to genuine corporate transition or merely improves the economics of one part of a diversified industrial portfolio depends on the circumstances.

What conditions are imposed on the wider company?

What monitoring is undertaken?

How are the financing benefits prevented from indirectly supporting other activities inconsistent with the stated environmental objectives?

And how does the EIB distinguish a genuine transformation of a high-emitting corporation from a more limited diversification of its revenue streams?

These questions are relevant beyond Livorno.


32. A wider public financing ecosystem

The Livorno financing cannot be considered entirely in isolation from ENI’s broader biorefining and agricultural strategy.

In April 2026, the EIB announced another €500 million financing agreement supporting the partial conversion of ENI’s Sannazzaro refinery into a biorefinery.

Together, these two financing agreements represent €1 billion in EIB lending for the industrial conversions.

Other public and international financing initiatives concern the development of agricultural feedstock.

The $210 million Kenyan financing package is one example.

Earlier European research programmes have also supported the development of advanced biofuel technologies.

These instruments differ substantially in purpose and financial structure.

Financial operationAmountNature
EIB Livorno€500 millionLoan financing
EIB Sannazzaro€500 millionLoan financing
IFC and Italian Climate Fund — Kenya$210 millionDevelopment financing
KKR transactions involving EniliveApproximately €3.6 billionPrivate equity transactions, including capital increase

The KKR transactions are private investment, not public funding.

The agricultural financing is not equivalent to a loan directly financing Livorno.

However, the combination illustrates the scale and complexity of the financial infrastructure supporting ENI’s renewable fuel strategy.

A comprehensive assessment should distinguish loans, grants, guarantees, tax incentives, regulatory support and private investment.

It should also establish whether the same industrial expenditure is financed or subsidised through more than one mechanism, and whether cumulative support is compatible with applicable rules.

The availability of public financing does not itself demonstrate that a project lacks commercial merit.

But when multiple public institutions support interconnected stages of an industrial value chain, the overall distribution of commercial benefits and risks deserves transparency.


33. The wider industrial context: lessons from ENI’s chemical transformation

The Livorno investigation takes place against the background of ENI’s broader transformation of its chemical and industrial businesses.

Bioplastics News has previously examined the financial difficulties of Versalis, the acquisition of Novamont and the historical performance of the Matrìca joint venture in Porto Torres.

Those cases involve different technologies, ownership structures and economic circumstances.

They should not be treated as interchangeable.

However, several recurring analytical questions deserve consideration across industrial conversion projects:

  • How is the commercial viability of new technologies assessed?
  • Are sufficient raw materials available at competitive prices?
  • Are there credible markets for the resulting products?
  • How much public financing supports the investments?
  • How are historical industrial liabilities managed?
  • What financial information is available at individual plant level?
  • Are related-party transactions adequately scrutinised?
  • Who ultimately benefits if the transformation succeeds?
  • Who bears the financial losses if it fails?

Livorno differs from many of the previously examined industrial cases because its future investment cost, principal construction contracts and public-bank financing have been disclosed to a significant extent.

However, the historical profitability of the conventional refinery and the projected financial performance of the new biorefinery remain less transparent.

These information gaps prevent an independent reconstruction of the complete investment decision.

The conversion may ultimately prove commercially successful.

It may also provide substantial environmental benefits.

Those possibilities should remain open.

But neither commercial success nor environmental success should be assumed before the evidence is available.


34. Questions for the European Investment Bank

Bioplastics News invites the European Investment Bank to clarify the following matters concerning project 2024-0694.

Financial appraisal and additionality

  1. What justified financing approximately 67.5% of the estimated project cost?
  2. Would Livorno have proceeded without EIB financing?
  3. What incremental public benefits result specifically from the EIB’s involvement?
  4. How did the bank reconcile the €420 million regional estimate with its €741 million estimate?
  5. Which individual expenditure categories are eligible under the financing agreement?
  6. Does the financing include the methane-based hydrogen production unit?
  7. Does it include soil excavation, waste treatment, historical remediation or related-party environmental services?
  8. What commercial viability and financial sensitivity analyses were performed?
  9. What is the anticipated economic return of the project compared with its financial return?
  10. Has the bank reassessed the investment following contract changes and schedule revisions?

Procurement and corporate relationships

  1. Did ENI organise a competitive procurement process for Saipem’s €300 million contract?
  2. Which competing offers or independent price benchmarks did the EIB examine?
  3. How did the bank assess the related-party nature of the Saipem transaction?
  4. Did the appraisal identify the corporate relationships involving ENI, CDP and Saipem?
  5. Were the principal contractors subjected to integrity and anti-corruption checks?
  6. Did the bank undertake a proactive integrity review?
  7. Did the EIB examine how financing costs and benefits would be allocated between ENI and Enilive?
  8. Was KKR’s 30% investment in Enilive considered during the appraisal?

Environmental liabilities

  1. Was the EIB aware of Livorno’s designation as a national remediation site?
  2. Did the bank independently assess historical soil and groundwater contamination?
  3. Did it examine the continuing groundwater containment obligations?
  4. Was it aware of the environmental criminal proceeding identified in judicial documentation in 2023?
  5. Why were these historical environmental matters not explicitly discussed in the public environmental assessment?
  6. Why were no specific environmental conditions precedent to disbursement identified in that document?
  7. What environmental monitoring and corrective action obligations apply to the loan?

Feedstock and carbon footprint

  1. What precise feedstock mix was assumed in the environmental appraisal?
  2. Which geographical origins and transportation routes were incorporated?
  3. Did the bank examine actual or proposed supply contracts?
  4. Did it consider the environmental impact of imported African or Asian agricultural and waste-derived feedstock?
  5. Did the Commission’s July 2025 findings concerning weaknesses in biofuel certification audits trigger additional verification?
  6. What natural gas consumption and hydrogen production assumptions were used?
  7. What land-use-change and methane leakage assumptions were incorporated?
  8. What sensitivity analysis was conducted?
  9. Will the bank publish the original carbon footprint calculation and its supporting assumptions?
  10. How will actual operational emissions be verified?

Waste management and industrial integration

  1. Was the bank aware of ENI Rewind’s historical waste-to-chemicals and waste-to-gas proposals for Livorno?
  2. Were any potential industrial connections between those projects and the biorefinery incorporated into the appraisal?
  3. Did the bank evaluate the estimated waste generated by the biorefinery itself?
  4. Were the transportation and treatment of those waste streams included in the environmental assessment?
  5. Has the bank examined whether future waste conversion activities could affect the carbon or energy balance of the financed project?

Governance and transparency

  1. Which EIB decision-makers participated in the delegated approval of the project?
  2. Which departments and individuals prepared the appraisal?
  3. Were any reservations or objections recorded?
  4. Were declarations of interests assessed specifically in relation to the ENI operation?
  5. Was the disclosed IAI–ENI institutional relationship considered in assessing potential conflicts of interest involving the EIB vice-president?
  6. Why was the project summary’s recorded release date later than both financing approval and signature?
  7. Was an exception to the Transparency Policy granted?
  8. Who requested and approved that exception?
  9. What information was provided to the European Commission under the applicable institutional procedure?
  10. Will the EIB release the underlying appraisal, procurement assessment and approval documentation, subject to justified and narrowly defined confidentiality restrictions?

35. Questions for ENI, Enilive, ENI Rewind and the principal contractors

The industrial companies involved in Livorno are invited to clarify the following matters.

ENI and Enilive

  • What were the historical financial results of the conventional Livorno refinery?
  • What alternative industrial strategies were examined before conversion?
  • What explains the difference between the original regional investment estimate and the EIB estimate?
  • What is the current total project budget?
  • What are the latest mechanical completion, commissioning and commercial production dates?
  • What contractual commitments exist for the supply of biological raw materials?
  • Which countries and suppliers will provide Livorno’s feedstock?
  • What proportion will originate outside Europe?
  • What commercial purchasing commitments exist for the final products?
  • What are the project’s projected revenues, profitability and return on investment?
  • How will financing costs and operating earnings be allocated between ENI and Enilive?
  • Was anticipated EIB financing considered in KKR’s investment valuation?
  • How much natural gas will be consumed by the new hydrogen installation?

ENI Rewind and ALIA

  • What is the current status of the historical Livorno waste-to-chemicals project?
  • What is the current status of the proposed waste-to-gas installation?
  • Were dedicated operating companies established?
  • Were any projects abandoned, postponed or transferred elsewhere?
  • Were potential industrial connections to the biorefinery envisaged?
  • Were compostable packaging materials or composting rejects intended as feedstock?
  • What was the anticipated destination of recovered methanol and biomethane?
  • What public funding or commercial arrangements were contemplated?
  • Which companies received the approximately 180,000 tonnes of excavated material associated with the conversion?
  • What proportion of that material required hazardous or contaminated waste treatment?

Saipem

  • Was the €300 million Livorno contract awarded following competitive tendering?
  • Were independent market benchmarks used?
  • How was the classification of the transaction as being conducted under market-equivalent conditions supported?
  • What documentation was submitted to CONSOB?
  • Has the original contract value changed?
  • Was the original third-quarter 2026 completion milestone achieved?
  • What contractual amendments or extensions have been agreed?

MAIRE and KT – Kinetics Technology

  • What explains the increase in the hydrogen plant contract value?
  • What caused the evolution of the commissioning schedule?
  • What additional or modified engineering requirements have been introduced?
  • Is the installation designed to operate exclusively with conventional natural gas, or can certified biomethane be substituted?
  • Could the facility receive hydrogen or processed synthesis gas from other industrial installations?
  • What is the expected natural gas consumption and carbon intensity of hydrogen production?

BIOREPACK and organic waste treatment operators

  • How are compostable packaging rejects measured and deducted from recycling statistics?
  • What proportion of compostable packaging is removed during pre-treatment or screening?
  • What proportion completes biological degradation?
  • What proportion is transferred to thermal treatment or other recovery operations?
  • Are the resulting figures independently audited?
  • Are the destination facilities and waste classification records publicly accessible?

36. A note on Bioplastics News’ original reporting

On 25 July 2025, Bioplastics News published a strongly critical article concerning the EIB’s €500 million financing agreement with ENI.

That article subsequently became relevant to legal proceedings initiated by ENI against the publisher.

The present investigation returns to the industrial and institutional circumstances surrounding the financing.

It incorporates documents and developments available before the original publication, documents prepared earlier but disclosed subsequently, and new information emerging during 2026.

These three categories must be distinguished.

Later discoveries cannot retrospectively be represented as information that was publicly available when the original article was written.

Nevertheless, subsequent disclosures can contribute to a fuller understanding of the underlying industrial project and the institutional questions it raises.

The publisher has a direct interest in the ongoing legal proceedings. That interest is disclosed here so that readers can assess the context of this investigation.

The findings should be evaluated on the strength of the original documents, independently of the publisher’s legal dispute with ENI.

This article does not assert that bribery or a criminal corruption scheme has been established in relation to the Livorno financing.

Its central concern is whether the available evidence and the applicable institutional safeguards adequately explain the financing decision.


37. Conclusion: the €500 million question

The Livorno biorefinery is not merely a project to replace petroleum with vegetable oils and waste-derived resources.

It sits at the intersection of several major industrial and financial developments:

The transformation of existing European refinery infrastructure.

The expansion of the renewable fuel market through legislation and public policy.

The internationalisation of agricultural feedstock supply chains.

The acquisition of compostable plastics businesses.

The development of alternative waste treatment technologies.

The use of methane and hydrogen in renewable fuel manufacturing.

The involvement of private equity investors.

The allocation of major construction contracts to related corporate entities.

And the growing role of public financial institutions in financing industrial transformation.

Examined separately, each component may have a reasonable industrial or commercial explanation.

Examined together, they raise questions that deserve considerably more transparency.

Why did the published investment estimate evolve from €420 million to €741 million?

How was the €300 million related-party construction contract priced?

Why was favourable public-bank financing selected by a multinational company that acknowledges its ability to access private capital?

How were historical environmental liabilities assessed?

Which future feedstock supply chains underpin the project?

What assumptions support the projected carbon footprint reduction?

What is the relationship, if any, between the biorefinery and the historical waste treatment proposals associated with the Livorno site?

What is the actual fate of compostable plastic waste within the wider industrial system?

And why did the EIB’s recorded project summary appear after the financing had already been approved and signed?

The answers may reveal legitimate industrial decisions supported by sound economic and environmental evidence.

They may also reveal deficiencies in procurement scrutiny, environmental assessment, project transparency or financial additionality.

The evidence currently available does not establish which explanation applies to every outstanding question.

But these are not peripheral details.

They concern the fundamental basis upon which a European public financial institution committed €500 million to an industrial project.

Europe’s energy transition will require substantial investment.

Its credibility depends not only on the amount of capital invested or the environmental terminology used to describe new projects, but also on whether those projects deliver independently verifiable environmental benefits, transparent procurement and economically defensible outcomes.

The circular economy cannot be assessed exclusively through diagrams showing potential industrial connections.

It must be assessed through actual material flows, actual energy consumption, actual carbon emissions and actual financial results.

And public financing must be accompanied by sufficient public accountability.

Ultimately, the most important question in the Livorno affair is this:

What precisely did the European Investment Bank know about the industrial, financial and environmental foundations of the project when it approved the €500 million financing — and what evidence justified its conclusions?

The European Investment Bank, ENI and the other institutions and companies involved are invited to answer.

Their explanations and any supporting documentation will be considered on their merits.


Sources and original documentation

European Investment Bank

1. ENI BIOREFINERY — Project 2024-0694.

Project cost, financing amount, procurement classification, approval and publication chronology.

https://www.eib.org/en/projects/all/20240694

2. Environmental and Social Data Sheet — 24 June 2025.

Environmental assessment, feedstock assumptions, projected emissions, Paris alignment and environmental undertakings.

https://www.eib.org/attachments/registers/243474616.pdf

3. EIB–ENI €500 million financing announcement — 24 July 2025.

https://www.eib.org/en/press/all/2025-296-eib-and-eni-sign-eur500-million-finance-agreement-to-convert-livorno-refinery-into-a-biorefinery

4. EIB Guide to Procurement — March 2024.

https://www.eib.org/files/publications/20240132_guide_to_procurement_for_projects_financed_by_the_eib_en.pdf

5. Decisions taken under delegated authority — June 2025.

https://www.eib.org/files/events/board-decisions-delegation-management-committee-june-2025.pdf

6. EIB Group Transparency Policy.

Policy adopted in November 2021 and subsequently amended in July 2025.

https://www.eib.org/en/publications/20250191-eib-group-transparency-policy

7. EIB transparency and public access to information.

https://www.eib.org/en/about/partners/cso/access-information/index.htm

8. Gelsomina Vigliotti — official curriculum vitae.

https://www.eib.org/en/readonline-publications/information-gelsomina-vigliotti

9. Gelsomina Vigliotti — declaration of interests.

https://www.eib.org/files/documents/declaration-interest-gelsomina-vigliotti-en.pdf

10. EIB–ENI Sannazzaro financing announcement — April 2026.

https://www.eib.org/en/press/all/2026-125-eib-and-eni-sign-eur500-million-in-financing-for-new-biorefinery-in-sannazzaro-de-burgondi

ENI and corporate financial documentation

11. ENI — Livorno refinery and conversion project.

https://www.eni.com/en-IT/actions/global-activities/Italy/livorno.html

12. ENI — Questions and answers prior to the 2026 shareholders’ meeting.

Includes financing terms, access to private capital, feedstock assumptions, environmental commitments, groundwater containment and excavation costs.

https://www.eni.com/content/dam/enicom/documents/eng/governance/shareholders-meetings/2026/Master-Q-A_en_Assemblea-2026.pdf

13. ENI — Questions and answers prior to the 2025 shareholders’ meeting.

https://www.eni.com/content/dam/enicom/documents/eng/governance/shareholders-meetings/2025/QA-AGM-2025.pdf

14. ENI — KKR acquisition of additional Enilive stake, April 2025.

https://www.eni.com/en-IT/media/press-release/2025/04/pr-eni-kkr-completes-acquisition-stake-share-capital-enilive.html

15. ENI annual report 2025.

https://report.eni.com/annual-report-2025/en

16. ENI annual report 2023, Form 20-F.

https://www.sec.gov/Archives/edgar/data/1002242/000155485524000249/e-20231231.htm

17. ENI — acquisition of Novamont completed, October 2023.

https://www.eni.com/en-IT/media/press-release/2023/10/versalis-acquisition-of-novamont-completed.html

18. ENI–BF agricultural partnership, November 2021.

https://www.eni.com/en-IT/media/press-release/2021/11/eni-and-bf-partnership-for-the-development-of-research-projects.html

Contractors and procurement

19. Confindustria Livorno Massa Carrara — principal construction contractors, 15 July 2024.

https://www.confindustrialivornomassacarrara.it/news.php?ID=37276

20. Cestaro Rossi — principal industrial projects and contract values.

https://www.cestarorossi.it/aggiornato/wp-content/uploads/2024/07/Cestaro-Rossi_Principali-lavori_ITA_2024_web-1.pdf

21. Saipem annual report 2024.

Includes the Livorno related-party transaction disclosure.

https://www.saipem.com/en/governance/governance-documents/annual-report-2024

22. Saipem — shareholders and joint control.

https://www.saipem.com/en/investors/shareholders

23. Saipem — related-party transaction governance procedures.

https://www.saipem.com/en/governance/transactions-related-parties

24. ENI–Saipem strategic cooperation agreement, November 2023.

https://www.saipem.com/en/media/press-releases/2023-11-06/eni-and-saipem-agreement-develop-new-biorefineries

25. ENI–Saipem extension of biorefining collaboration, March 2025.

https://www.saipem.com/en/media/press-releases/2025-03-27/eni-and-saipem-extend-collaboration-agreement-biorefining

26. MAIRE — original hydrogen plant contract announcement.

https://www.groupmaire.com/en/newsroom/press-releases/detail/kt-maire-awarded-contract-by-eni-worth-123-million-for-a-hydrogen-production-unit-as-part-of-the-livorno-plant-conversion-into-a-biorefinery

27. MAIRE annual financial report 2025.

https://www.groupmaire.com/en/governance/shareholders-documents/

28. MAIRE half-year financial reporting 2026.

https://www.groupmaire.com/en/investors/financial-results/

Italian environmental, parliamentary and industrial documentation

29. Official Bulletin of the Tuscany Region — 15 May 2024.

Original €420 million investment estimate.

https://www.regione.toscana.it/documents/10180/203230754/PARTE%2BII%2Bn.%2B20%2Bdel%2B15.05.2024.pdf/f46ad887-6d87-25de-ad0b-68b68a99fbd2?t=1715753259438

30. Italian Ministry of Environment — Livorno environmental procedures.

https://va.mite.gov.it/it-IT/Oggetti/Info/9500

31. Updated biorefinery technical documentation, 2026.

https://va.mite.gov.it/it-IT/Oggetti/Documentazione/9500/18837

32. Italian Senate — response concerning Livorno remediation.

https://www.senato.it/show-doc?id=1410322\u0026leg=19\u0026tipodoc=Sindispr

33. Italian Chamber of Deputies — parliamentary question concerning historical contamination, July 2018.

https://storia.camera.it/documenti/indirizzo-e-controllo/20180730-4-00831-interrogazione-risposta-scritta-4-00831-presentata-ripani-elisabetta-forza-italia-1

34. Italian Senate — historical refinery withdrawal and sale discussions.

https://www.senato.it/show-doc?id=394752\u0026idoggetto=0\u0026leg=16\u0026tipodoc=Sindisp

35. ARPAT technical report concerning Tuscany waste planning.

Includes the status of proposed Livorno waste projects, indicative geographical origins of biorefinery feedstock and projected waste generation.

https://www.regione.toscana.it/documents/10180/23121876/Allegato%2Brifiuti.pdf/0c2cc22a-6b6e-82a6-f866-6ec9922032e1?t=1704800162810

36. Tuscany Region — ENI–ALIA agreement, July 2019.

https://www301.regione.toscana.it/bancadati/atti/Contenuto.xml?id=5222765&nomeFile=Delibera_n.866_del_05-07-2019-Allegato-A

37. Tuscany waste planning preliminary environmental documentation, 2019.

https://www.regione.toscana.it/documents/10180/22524463/Documento%2Bpreliminare%2BVAS%2Bmodifica%2BPiano%2BRifiuti%2B26.07.19.pdf/170046e5-f57a-88cc-29ee-26391068731a?t=1576595274886

38. Florence judicial authorities — October 2023 report.

Includes environmental criminal proceeding No. 2565/2021 RGNR.

https://pg-firenze.giustizia.it/cmsresources/cms/documents/timbrato_-_2023-10-31T130612.137.pdf

International feedstock and agricultural financing

39. IFC and Italian Climate Fund — $210 million Kenyan financing initiative.

https://www.ifc.org/en/pressroom/2024/ifc-and-the-italian-climate-fund-partner-with-eni-to-support-biofuel-production-farmers-in-kenya

40. IFC Kenya project disclosure.

https://disclosures.ifc.org/project-detail/SII/47491/eni-biofuel-ken

41. IFC Kenya environmental and social review.

https://disclosures.ifc.org/project-detail/ESRS/47491/eni-biofuel-ken

42. Transport & Environment — Not What They Promised, March 2026.

Investigation into ENI’s African agricultural supply chain.

https://www.transportenvironment.org/articles/not-what-they-promised

43. ENI — response concerning its Kenyan agricultural projects.

https://www.eni.com/en-IT/actions/energy-sources/bioenergy/agrifeedstock-press-faq.html

44. European Commission — examination of potential Chinese biofuel imports fraud, 18 July 2025.

https://energy.ec.europa.eu/news/commission-concludes-examination-potential-chinese-biofuel-imports-fraud-2025-07-18_en

Compostable plastics and recycling methodology

45. European Environment Agency — Biodegradable and compostable plastics: challenges and opportunities.

https://www.eea.europa.eu/en/analysis/publications/biodegradable-and-compostable-plastics-challenges-and-opportunities

46. Eurostat — Guidance for the compilation and reporting of data on packaging and packaging waste.

See in particular the provisions concerning combined biological treatment and energy recovery and the exclusion of compostable packaging rejects.

https://ec.europa.eu/eurostat/cache/metadata/Annexes/env_waspac_esms_an_Guidance_on_packaging_and_pack.pdf

47. BIOREPACK — 2024 recycling performance.

https://www.biorepack.org/en/press-releases/assembly-2024

Institutional accountability and historical compliance proceedings

48. Istituto Affari Internazionali — strategic partnership with ENI.

https://www.iai.it/en/research/iai-eni-strategic-partnership

49. European Ombudsman — EIB transparency case 3/2023/OAM.

https://www.ombudsman.europa.eu/en/decision/en/172566

50. US Securities and Exchange Commission — ENI settlement, Algeria-related accounting and internal control proceedings, April 2020.

https://www.sec.gov/enforcement-litigation/administrative-proceedings/34-88679-s

51. Saipem — definitive acquittal in the Italian Algeria proceedings, December 2020.

https://www.saipem.com/en/media/press-releases/2020-12-14/saipem-court-cassation-rejected-appeal-general-public-prosecutor

52. US Department of Justice — Snamprogetti Nigeria deferred prosecution agreement, July 2010.

https://www.justice.gov/archives/opa/pr/snamprogetti-netherlands-bv-resolves-foreign-corrupt-practices-act-investigation-and-agrees

Independent press reporting

53. Il Tirreno — Livorno biorefinery construction and anticipated start-up, June 2026.

https://www.iltirreno.it/livorno/cronaca/2026/06/23/news/livorno-dentro-alla-nuova-bioraffineria-eni-duemila-persone-al-lavoro-come-sara-la-fabbrica-dei-carburanti-1.100886521

54. Il Tirreno — historical fuel theft proceedings, February 2019.

https://www.iltirreno.it/livorno/cronaca/2019/02/04/news/furti-di-carburante-alla-raffineria-eni-dopo-sette-anni-condannati-18-autisti-1.17722973

Continue Reading

More coverage on the subjects, companies and places discussed in this article.

Explore this category

, , , , , , ,

More on these companies, countries & topics

Discover more from Bioplastics News

Subscribe to get the latest reporting in your inbox.